Project Schedules: What to Expect
One of the first questions clients ask is, “How long is this going to take?” This table outlines typical schedules for three types of project: new construction, a large remodel, and a small remodel. Please remember that every project is unique and actual timelines may vary from these rules of thumb, depending on specific conditions.
Project Phases | New Construction | Large Remodel | Small Remodel |
Pre-Design Confirm site conditions Establish project profile | 3-4 weeks | 2-4 weeks | 1-3 weeks |
Schematic Design Concept sketches “Process of Discovery” Presentation drawings Contractor selection Cost analysis | 4-6 weeks | 2-4 weeks | 2-3 weeks |
Design Development Computer drawings Interior elevations Outline specification Structural analysis Cost analysis | 3-4 weeks | 2-3 weeks | 2-3 weeks |
Construction Documents Permit drawings Permit submission Final specifications Finish details Interior drawings Construction contract analysis | 8-18 weeks | 6–12 weeks | 4-8 weeks |
Construction Supervision Weekly site supervision | 8-20 months | 4-8 months | 2-4 months |